CLIENT PROJECT CONTRACT DURATION CONTRACT PRICE (MILLION RIALS) CONTRACT STARTING DATE PERCENT PROGRESS LOCATION Certificate of Excellence
SAFF South Pars Oil Layer 6 Month - 2007 47.26% Persian Gulf In Progress
NIOC - Petroiran Foroozan and Esfandiar 24 Month 259 million USD 2004 2.29% Persian Gulf In Progress
IOOC Cost Benchmarking and field operation efficiency / Best practices for Aboozar Field 9 Month 920,000 USD 2004 100% Persian Gulf / Aboozar Oil Field Good Performance Certificate
IOOC Resalat Field Renovation Reconstruction 9 Month 4.5 Million USD 2004 100% Persian Gulf Good Performance Certificate
NIOC - Petroiran Salman EPC-3 Pipes Sub Sea Cable Installation 24 Month 1,200,000 Equivalent to 150 Million USD 2003 83.36% Persian Gulf In Progress
IRAL CO. Jajarm Alumina Production Plant (II) 4 Month 2.353 2001 100% Jajarm - Khorasan Province Good Performance Certificate
PEDEC Central Oil Fields Development Projects 1 Years 1,989 2001 100% Khozestan
Ilam
Fars
Boushehr
Good Performance Certificate
Shahid Tondgooyan Petrochemical Co. Structure Design Certification 1 Years 275 2001 100% Tehran Good Performance Certificate
IOOC Aboozar Field Sub sea Cable Installation Management Services 6 Month 100 2001 100% Tehran --
NICICO Congou Copper 10 Month 2.684 1999 100% Ahar Good Performance Certificate
IOEC Engineering Services South Pars (Phase I ) SPD 1 Platform Installation 1 Year 1.640 1998 100% Persian Gulf
South Pars Gas Field
Good Performance Certificate
IRAL CO. Jajarm Alumina Production Plan 5 Years 29.231 1996 100% Jajarm - Khorasan Province Good Performance Certificate
IOEC Project Management EPC - South Pars (Phase II ) Drilling Platform 3 Years 5.45 1996 100% Persian Gulf
South Pars Gas Field
Good Performance Certificate
SADRA Preparation of Tender Documents for
South Pars Gas Field
(phase I)
6 Month 100 1996 100% Tehran Good Performance Certificate